The Critical Path is the sequence of activities that represents the longest path through a project, determining the shortest possible duration for project completion. Any delay in a critical path activity directly impacts the project’s finish date.

Key Aspects of the Critical Path

  • Determines Project Duration – Defines the minimum time needed to complete the project.
  • Identifies Critical Activities – Tasks on the critical path cannot be delayed without extending the project timeline.
  • Has Zero Float (Slack) – Critical tasks have no scheduling flexibility.
  • Used in the Critical Path Method (CPM) – Helps in scheduling, resource allocation, and risk management.

Example Calculation of Critical Path

ActivityDuration (Days)Predecessor
A3Start
B5A
C2A
D4B
E6C
F3D, E
G (End)2F

Critical Path Determination

  1. Identify all paths through the project network.

    • Path 1: A → B → D → F → G → (Total: 3+5+4+3+2 = 17 days)
    • Path 2: A → C → E → F → G → (Total: 3+2+6+3+2 = 16 days)
  2. Select the longest path.

    • Critical Path: A → B → D → F → G (17 days)

Mermaid Diagram: Critical Path Example

graph LR;
    Start["Project Start"] --> A["Task A (3d)"]
    A --> B["Task B (5d)"]
    A --> C["Task C (2d)"]
    B --> D["Task D (4d)"]
    C --> E["Task E (6d)"]
    D --> F["Task F (3d)"]
    E --> F
    F --> G["Task G (2d)"]
    G --> End["Project Completion"]
    class A,B,D,F,G critical;

Why the Critical Path Matters

  • Defines the Minimum Project Duration – Helps set realistic completion deadlines.
  • Highlights High-Risk Activities – Delays in critical path tasks directly impact the schedule.
  • Aids in Resource Allocation – Focuses attention on critical activities requiring priority resources.
  • Enables Proactive Schedule Management – Allows project teams to anticipate and mitigate potential delays.

See also: Critical Path Activity, Critical Path Method (CPM), Schedule Network Diagram, Total Float.