A Critical Path Activity is any activity on the critical path in a project schedule. These activities directly impact the project’s finish date because they have zero float (slack)—meaning any delay will extend the overall project duration.

Key Aspects of a Critical Path Activity

  • Essential for Project Completion – Delays in these activities push back the entire project.
  • Has Zero Float – No flexibility in scheduling.
  • Forms the Longest Path in the Project – Determines the shortest possible project duration.
  • Requires Close Monitoring – Must be tracked to prevent project overruns.

Example: Identifying Critical Path Activities

ActivityDuration (Days)PredecessorOn Critical Path?
A3Start✅ Yes
B5A✅ Yes
C2A❌ No
D4B✅ Yes
E6C❌ No
F3D, E✅ Yes
G (End)2F✅ Yes
  • Critical Path: A → B → D → F → G (Total Duration: 17 days)
  • Critical Path Activities: A, B, D, F, G

Mermaid Diagram: Critical Path Activities

graph LR;
    Start["Project Start"] --> A["Task A (3d)"]
    A --> B["Task B (5d)"]
    A --> C["Task C (2d)"]
    B --> D["Task D (4d)"]
    C --> E["Task E (6d)"]
    D --> F["Task F (3d)"]
    E --> F
    F --> G["Task G (2d)"]
    G --> End["Project Completion"]
    class A,B,D,F,G critical;

Why Critical Path Activities Matter

  • Directly Impact the Project Deadline – Any delay in these tasks extends project completion.
  • Require Priority Monitoring – High-risk tasks needing focused tracking.
  • Help in Resource Allocation – Ensures critical tasks get necessary resources.
  • Enable Proactive Risk Management – Identifies potential bottlenecks early.

See also: Critical Path, Critical Path Method (CPM), Schedule Network Diagram, Total Float.