Earned Value Management (EVM) is a methodology that integrates scope, schedule, cost, and resource measurements to assess project performance and progress. It provides a structured approach to tracking project health using quantitative data.

Key Aspects of Earned Value Management

  • Combines Scope, Schedule, and Cost – Ensures all aspects of project performance are evaluated together.
  • Uses Key Performance Metrics – Analyzes project efficiency through Earned Value (EV), Actual Cost (AC), and Planned Value (PV).
  • Enables Forecasting – Helps predict cost overruns and schedule delays.
  • Supports Proactive Decision-Making – Identifies deviations early for corrective actions.

Core EVM Metrics

MetricFormulaDescription
Earned Value (EV)% Work Completed × BACValue of work performed based on budgeted cost.
Planned Value (PV)Planned % of BACBudgeted cost for work scheduled at a given point.
Actual Cost (AC)Sum of all incurred costsTotal cost spent on completed work.
Cost Performance Index (CPI)EV ÷ ACMeasures cost efficiency (CPI > 1 is under budget).
Schedule Performance Index (SPI)EV ÷ PVMeasures schedule efficiency (SPI > 1 is ahead of schedule).

Mermaid Diagram: EVM Workflow

graph LR;
    A["Project Plan"] -->|Planned Value (PV)| B["Work Scheduled"]
    B -->|Earned Value (EV)| C["Work Completed"]
    C -->|Actual Cost (AC)| D["Cost Incurred"]
    D --> E["Performance & Forecasting"]

Example Scenarios

Software Development

A project with a BAC of $500,000 is 40% complete but has an AC of $250,000.

  • EV = $200,000, CPI = 0.8 (Over budget)
  • SPI = 1.0 (On schedule)

Construction Project

A bridge project planned for 6 months is at 50% completion, but only 40% of budgeted funds have been used.

  • CPI = 1.25 (Under budget)
  • SPI = 0.8 (Behind schedule)

Marketing Campaign

A company planned to launch a campaign in 3 months with a budget of $100,000.
At month 2, 70% of the work is complete, but 80% of the budget is spent.

  • CPI = 0.875 (Over budget)
  • SPI = 1.16 (Ahead of schedule)

Why Earned Value Management Matters

  • Provides Objective Performance Measurement – Tracks real project progress.
  • Identifies Budget & Schedule Variances Early – Helps avoid cost overruns.
  • Supports Forecasting & Risk Management – Predicts future project trends.
  • Improves Stakeholder Confidence – Offers data-driven insights.

See also: Earned Value (EV), Planned Value (PV), [[Actual Cost (AC), Cost Performance Index (CPI), Schedule Performance Index (SPI), Budget at Completion (BAC).