A Near-Critical Path is a sequence of scheduled activities that possesses low total float, meaning it is close to becoming a critical path if any additional delay occurs. Though not currently the longest path through the schedule, it presents a significant schedule risk because its buffer is minimal and easily consumed.
Purpose and Characteristics
- Low Total Float Threshold – Typically flagged when float is within a narrow range (e.g. 0–2 days).
- Not Currently Critical – But it can quickly become critical with minor slippage.
- Monitored Closely – Especially in high-risk or resource-constrained projects.
- Shifts Dynamically – Changes in duration or float on any path can cause near-critical paths to become critical.
Example Scenario
If a project has two primary sequences of activities—one with zero float (critical) and another with one day of float (near-critical)—any delay in the near-critical path puts the overall delivery date at risk, effectively turning it into a second critical path.
Mermaid Diagram: Path Classification by Float
flowchart LR subgraph Critical Path direction LR A1[Start] --> A2[Task A - Float 0] --> A3[Task B - Float 0] --> A4[End] end subgraph Near-Critical Path direction LR B1[Start] --> B2[Task C - Float 1] --> B3[Task D - Float 1] --> B4[End] end subgraph Non-Critical Path direction LR C1[Start] --> C2[Task E - Float 5] --> C3[Task F - Float 5] --> C4[End] end
This visual highlights how multiple paths flow toward project completion, with only small differences in float separating near-critical from critical status.
Why Near-Critical Paths Matter
- Indicate Schedule Fragility – Show how close the project is to delay risks beyond the known critical path.
- Enable Focused Monitoring – Help prioritize additional tracking and resource management.
- Improve Risk Response Readiness – Support early intervention to avoid cascading delays.
See also: Critical Path, Near-Critical Activity, Total Float, Free Float.