Planned Value (PV) is the authorized budget assigned to scheduled work at a specific point in time. It represents how much of the budget should have been spent, according to the project schedule, regardless of actual progress or performance.

PV is a foundational element of earned value management (EVM) and is used to evaluate cost and schedule performance.

Key Characteristics

  • Time-Based Budget Reference – Tied directly to the schedule
  • Baseline-Driven – Calculated from the performance measurement baseline
  • Excludes Actual Progress – Independent of work performed or cost incurred
  • Used in Variance Calculations – Compared with EV and AC for performance insight

Example Scenarios

  • By week 6, a project is planned to have completed $200,000 worth of work—this is its PV
  • A monthly PV curve helps track budgeted progress against actual performance
  • PV is used to determine if the project is on pace financially and temporally

Why Planned Value Matters

  • Establishes a Baseline – Sets the reference for comparing actual and earned value
  • Supports Performance Metrics – Enables calculation of schedule variance and SPI
  • Improves Forecasting – Allows early detection of slippage or overrun
  • Drives Cost Control – Informs decision-making around resource use and pacing

See also: Actual Cost (AC), Earned Value (EV), Budget at Completion (BAC), Estimate at Completion (EAC), Estimate to Complete (ETC).