Program Evaluation and Review Technique (PERT) is a technique used to estimate project duration when there is uncertainty in activity estimates. It applies a weighted average formula to combine the optimistic, most likely, and pessimistic durations for each activity, producing a more realistic expectation of how long the activity will take.

PERT is particularly useful for projects with high variability or limited historical data.

Key Characteristics

  • Three-Point Estimating – Uses optimistic (O), most likely (M), and pessimistic (P) durations
  • Weighted Formula – Places more emphasis on the most likely estimate
  • Focuses on Uncertainty – Designed for activities with unclear or variable durations
  • Used in Network Analysis – Supports schedule modeling and critical path calculations

Example Scenarios

  • A research project with experimental tasks uses PERT to account for possible delays
  • Product development work with new technologies applies PERT to plan realistic timelines
  • Estimating the duration of an approval process with wide variability across stakeholders

PERT Formula (Expected Duration)

Mermaid Diagram: PERT Components and Flow

flowchart TD
    A[Optimistic Duration-O]
    B[Most Likely Duration-M]
    C[Pessimistic Duration-P]
    A --> D[PERT Formula]
    B --> D
    C --> D
    D --> E[Expected Duration-E]

Role in Project Estimation

  • Accounts for Uncertainty – Produces a more realistic activity duration
  • Improves Planning Accuracy – Balances best-case and worst-case possibilities
  • Supports Critical Path Method (CPM) – Enhances schedule modeling under risk
  • Useful in High-Variability Work – Ideal when little reliable data is available

See also: Analogous Estimating, Bottom-Up Estimating, Parametric Estimating, Multipoint Estimating, Three-Point Estimating.