Actual Duration is the total time, measured in calendar units, between the actual start date of a scheduled activity and either the project’s data date (if the activity is in progress) or the actual finish date (if the activity is complete). It provides a real measure of how long an activity has taken compared to initial estimates.

Key Aspects of Actual Duration

  • Reflects Real Execution Time – Measures the true time spent on an activity.
  • Dynamic Measure – If an activity is ongoing, the actual duration is updated up to the current data date.
  • Used for Performance Tracking – Compared against planned duration to assess schedule efficiency.
  • Expressed in Calendar Units – Typically measured in days, weeks, or months.

Example Scenarios

Software Development Project

  • Planned Duration for Feature Development: 10 days
  • Actual Start Date: March 1
  • Actual Finish Date: March 14
  • Actual Duration: 14 days (delayed by 4 days)

Construction Project

  • Planned Duration for Foundation Work: 20 days
  • Actual Start Date: April 10
  • Data Date (Current Status): April 25 (Work still in progress)
  • Actual Duration: 15 days (as of April 25)

Why Actual Duration Matters

  • Enhances Schedule Accuracy – Helps refine future project time estimates.
  • Supports Performance Analysis – Used to compare planned vs. actual execution times.
  • Aids in Delay Management – Identifies potential schedule risks early.

See also: Activity, Activity List.